A contract for construction and maintenance works for the task:
“Work on the rail line no. 7 Warszawa – Dorohusk, on the Warszawa – Otwock – Dęblin – Lublin, Otwock – Lublin section, in km 26.050-175.850 – “Partial Order C1 – Dęblin – Lublin section, in km 107.293 – 146.320””.
Contract delivery date: 30/06/2020.
The scope of works covered:
– construction of track and catenary system type YC150-2CS150 – 83.224 km
– construction of track and catenary system type C95-2C – 9.025 km
– construction of track and catenary system type C95-C – 9.354 km
– construction of collective traction structure bonding AFL6-120 – 71.837 km
The scope of works completed and put into operation as of 16/06/2020:
– construction of track and catenary system type YC150-2CS150 – 49.641 km
commissioned – 9.606 km
– construction of track and catenary system type C95-2C – 5.781 km
– construction of track and catenary system type C95-C – 4.954 km
– construction of collective traction structure bonding AFL6-120 – 48.261 km
commissioned – 8.859 km
The above works were completed for Budimex S.A.